27 june 2016
Since the last update there have been more delays in the aftermath of the North Tasmanian floods, but suddenly things started to happen : the lower floor framing went up and we could start to check the orientation and height of windows. We were very happy that most window openings showed what we expected. More steelwork bracing and beams were put into place and in the last few days the Bondek TM arrived and was positioned ready for the garage slab . Then all the first floor Hyspan TM joists came on site and on Saturday were placed on the lower floor framing, showing the extent of the upper floor, especially the high cantilever for the external decks and nook, very satisfying. We can only hope that the weather remains reasonably kind in the coming weeks allowing more rapid progress.